Firm News: indemnity

First Department finds factual issues in §241(6) exclusion, and holds that claim by a lessee’s contractor triggers the lessor’s indemnity

Permalink

By: Michael E. Kar, Esq.
       Associate, N.Y.

Date: December 27, 2017

Synopsis:

            On March 1, 2018, the First Department entered their decision in Karwowski v. 1407 Broadway Real Estate LLC. This decision gleans two important considerations for insurers and practitioners, in the Appellate Division’s: (i) holding that a lessor’s indemnity provision will be triggered by a claim by a lessee’s contractor; and (ii) finding of factual issues with the lower court’s exclusion of a contractor’s workshop from liability under 241(6).

Background:

            Defendant 1407 Broadway Real Estate LLC (“Broadway”) is the owner of the building wherein this claim arose. Broadway holds an operating lease for the entirety of the building, located in Midtown Manhattan, New York. Defendant Cayre Grp Ltd. (“Cayre”) leases the 41st and 42nd floors of Broadway’s building, and holds a lease extension with Broadway. Plaintiff is a former employee of XCEL Interior Contracting, Inc. (“XCEL”), a third-party defendant in the action. While employed by XCEL, Plaintiff injured his hand while cutting plywood on an unprotected table saw, located on the 16th floor of Broadway’s building. Plaintiff’s injury was in the furtherance of a project undertaken by Cayre, for which XCEL was hired as a contractor.

Indemnity Trigger:

            Pursuant to the lease extension with Broadway, Broadway was given direction and coordination over XCEL, who was one of the lease’s memorialized approved contractors (“[a]ll work done by the contractor [XCEL] must be coordinated with the Building Manager”). This lease extension also contained the following indemnity, recited in pertinent part: “Tenant shall indemnify, defend and save harmless Landlord… from and against (a) all claims of whatever nature against Landlord arising from any act, omission or negligence of Tenant, its subtenant, contractors, licensees, agents, servants, invitees, employees or visitors…”

            Broadway cross-claimed below for summary judgment as to the issue of their contractual indemnification, a claim that was not granted. The First Department reversed and found for Broadway on this issue. The Appellate Division found that this indemnity was clear and unambiguous. In response, Cayre argued that this provision required a finding of “active negligence” or fault on behalf of Cayre. The First Department disagreed with this assertion, in holding that “all that is necessary to trigger the provision is a claim arising from any act or omission of Cayre or Cayre’s contractor…” (emphasis added). Cayre’s contractor here was XCEL, employer of the Plaintiff at the time of the alleged accident. The court held that no negligence was needed to trigger the indemnity, and instead, all that was needed was work being done by Cayre or their contractors within the building leased by Broadway.


Factual issue found in Labor Law §241(6) analysis:

           At the Supreme Court below, Plaintiff’s claims under Labor Law §241(6) were dismissed. Section 241(6) imposes on property owners (and lessee’s under Article 10 of New York Labor Law) the duty to provide reasonable protection and safety for workers, and to comply with all Department of Labor regulations. The issue in application of §241(6) was, primarily, centered around the physical location at which the injury took place. The location was the 16th floor of the building in question. A portion of the 16th floor was XCEL’s in practice, an area where they would keep materials and tools used for renovations within the building. However, no personnel or office furniture existed in a permanent capacity, and XCEL had no lease and did not pay any rent for the space. XCEL maintains a separate permanent office and workshop in Queens.

          In support of their motion for summary judgment as to the applicability of Labor Law §241(6), Defendant Cayre asserted that the 16th floor is a permanent workshop where “for the past 10 years, the… plaintiff reported to work each day….” Their argument concludes that due to these facts the 16th floor is not the statutorily protected “area[] in which construction, excavation or demolition work is being performed….” N.Y. Labor Law §241(6).

            In granting Cayre’s motion for summary judgment below, the Supreme Court found that the 16th floor of the building “was a permanent workshop controlled by XCEL, not a temporary staging area ancillary to the Project and controlled by Cayre.” By extension, this also released Broadway under §241(6).

            The First Department reversed and remanded for the court below, finding that “there are disputed issues of fact concerning whether the 16th floor space qualifies as a construction area.” In remanding, the Appellate Division cited such cases as Gerrish v. 56 Leonard, 147 A.D.3 511 (1st Dept. 2017) (factors for determining applicability of 241(6) are physical proximity, common ownership, and operation of off-site premises) and Gonnerman v. Huddleston, 78 A.D.3d 993 (2d Dept. 2010) (241(6) extends to areas where materials are being readied for use, contrary to areas where materials are merely stored for future use).

            Lastly, and most important for Labor Law practitioners, the First Department then reasoned that because §241(6) would apply if the saw had been utilized on the 41st floor, the Plaintiff should not have an “automatic loss of the protections afforded by the statute” because Plaintiff chose instead to cut the wood on the 16th floor, and then bring it up to the 41st floor in an elevator.

            Application of this trigger to indemnity warrants widespread consideration across the legal universe. The analysis of Labor Law §241(6) by the First Department should be applied by insurance carriers and Labor Law practitioners to all future cases concerning the Section. Insurers should be aware that the designation of a physical area as a construction area is increasingly subject to more liberal interpretations – especially in regards to defense-side summary judgments motions.
241(6), contract law, contracts, Gartner + Bloom, indemnity, indemnity provision, labor law, Michael E. Kar

Arbitrating Indemnity Issues During the Pendency of a Supreme Court Action, by Arthur Xanthos

Permalink
Our last article warned of a pitfall with the traditional arbitration clause - ‎an arbitrator may end up with a power (e.g., the power to award punitive damages) that was never intended by the parties. Here we highlight another arbitration issue that has arisen several times in our practice.

Assume an Owner (O) hires a General Contractor (GC) to do work on a construction site, and the standard AIA form contract is executed containing a mandatory arbitration clause providing that "all disputes between the parties arising out of this agreement shall be resolved by binding arbitration under then applicable commercial arbitration rules". Plaintiff-worker (P) trips and falls while working on the site and sues both O and GC, alleging ‎negligence, as well as violations of the New York State Labor Law (the "Lawsuit"). O and GC each answer the Lawsuit and assert cross-claims against each other for contribution, defense, and indemnification.

All of the above is standard fare and occurs almost reflexively. But then something unusual happens: O's counsel files an arbitration demand, demanding that ‎GC arbitrate the issue of whether GC owes O defense and indemnification in the Lawsuit (the "Arbitration"). Inter-defendant arbitration of an indemnity obligation in the context of a pending personal injury lawsuit is an unusual tactic, and raises a host of procedural problems. For example, what happens to the rest of the case as the arbitration proceeds? What if the arbitration requires the resolution of other issues that have not yet been decided by the court? What if the arbitration takes the case beyond “standards and goals”? New York courts have come up with methods of dealing with the procedural problems. See, e.g., Weiss v Nath, 97 A.D.3d 661, 664 (2d Dep't 2012); County Glass & Metal Installers, Inc. v. Pavarini McGovern, LLC, 65 A.D.3d 940, 940-941 (1st Dep't 2009); and 624 Art Holdings, LLC v. Berry-Hill Galleries, Inc., 2012 N.Y. Misc. LEXIS 6440, 26-27 (N.Y. Sup. Ct. June 7, 2012). But even assuming counsel is willing to navigate the attendant procedural problems, in our opinion inter-defendant Arbitration of part of a Supreme Court action can only be justified in one of two circumstances:

1. Where a quicker resolution of the indemnity issue would occur in the Arbitration as opposed to the Lawsuit, and that speed is worth the arbitration fees; and/or
2. Where a more favorable resolution of the indemnity issue would occur in the Arbitration as opposed to the Lawsuit.

It is likely that New York counsel always will conclude that a quicker resolution would occur in the Arbitration. Counsel could also conclude that a more favorable resolution would occur in the Arbitration under the following scenarios:

1. If the rules applicable to the Arbitration (but not applicable to the Lawsuit) generate a better result -- of course then Arbitration would be advisable. But to make this decision counsel must retrieve the applicable Arbitration rules, review them for application to the indemnity issue, and compare the result with that obtained via the Lawsuit.
2. If the particular arbitrator used comes from a construction background and therefore knows or “feels” that such indemnity obligations should regularly be enforced -- here too Arbitration would be advisable.

So the conclusions are these: If the Arbitration would yield a more favorable result, choose inter-defendant arbitration regardless of the fees for arbitration. If the arbitration would yield a quicker result, and a result no worse than that yielded in Supreme Court, choose to arbitrate if you are willing to pay the cost to arbitrate in exchange for a speedier decision. In all other cases, bide your time and wait for the assigned Justice to make the decision on summary judgment.

APX 10/8/14
ADR, alternative dispute resolution, arbitration, Arthur Xanthos, construction law, general contractors, indemnification, indemnity, insurance, labor law, lawsuit, personal injury, premises liability, real estate